- Coordination must be conducted with all relevant entities, obtaining electronic governmental approvals within the request workflow.
- Once the request is approved by the coordination and approval entities and the Coordination Office, it is forwarded to the mayor for final approval.
- Commitment to attaching a traffic safety plan around the project site and addressing any consequences resulting from violations of the plan.
- Compliance with any updates from the Project Coordination Office regarding the maintenance of the project perimeter.
- Adherence to the work plan schedule for the project's phases submitted in the coordination request.
Notes/Reminders:
- The project coordination report must be obtained before proceeding with the building permit issuance for the site.