What are the requirements for a Certificate of Occupancy?
To issue a certificate of occupancy requires:
1- The existence of a previous license issued 6 months ago or more, and no occupancy certificate has been issued for it before.
2- Payment of service fees.
3- Contracting with an engineering office for non-residential uses.
4- Payment of violations.
1- The existence of a previous license issued 6 months ago or more, and no occupancy certificate has been issued for it before.
2- Payment of service fees.
3- Contracting with an engineering office for non-residential uses.
4- Payment of violations.
FAQ
What are the requirements for a site preparation permit?
● A survey decision for the site.
● Approval from the municipality or relevant authority.
● Approval from the municipality or relevant authority.
FAQ
What are the requirements for adding a consultant to the project team?
To add a consultant to the permit application project team, the following conditions must be met:
● A valid license number for the engineering consulting office must be available.
● A valid National Establishment Number (700 number) for the consulting office must be available.
● The classification must be valid.
● The consultant must be approved by the Coordination Office.
● A valid license number for the engineering consulting office must be available.
● A valid National Establishment Number (700 number) for the consulting office must be available.
● The classification must be valid.
● The consultant must be approved by the Coordination Office.
FAQ
What are the requirements for adding a consultant to the project team?
To add a consultant to the permit request team, the following requirements must be
met:
● Verification of a valid and active engineering consultancy office license
number.
● Verification of a valid and active National Establishment Number (700) for the
engineering consultancy office.
● Verification of the consultant's classification validity.
● The consultant must be approved by the Coordination Office.
met:
● Verification of a valid and active engineering consultancy office license
number.
● Verification of a valid and active National Establishment Number (700) for the
engineering consultancy office.
● Verification of the consultant's classification validity.
● The consultant must be approved by the Coordination Office.
FAQ
What are the requirements for the new authorized representative?
The authorization must be valid, and the representative must be authorized for the same service for which requests are being transferred.
FAQ
What are the Requirements for the Scheduled Project Coordination Service?
● The project owner must submit the request within a specified deadline each calendar year to have it classified as a Scheduled Project.
● The applicant's status must be verified:
○ If the applicant is a Business Owner/Establishment Manager, verification is conducted through the Ministry of Commerce.
○ If the applicant is an Authorized Representative, verification is done through the Balady Authorization Service.
● The project must meet the major construction project criteria defined by each municipality, based on area, budget, and number of floors.
● There must be no spatial or temporal conflict with any other scheduled project.
● The applicant must acknowledge and approve the service-related terms and conditions
● The applicant's status must be verified:
○ If the applicant is a Business Owner/Establishment Manager, verification is conducted through the Ministry of Commerce.
○ If the applicant is an Authorized Representative, verification is done through the Balady Authorization Service.
● The project must meet the major construction project criteria defined by each municipality, based on area, budget, and number of floors.
● There must be no spatial or temporal conflict with any other scheduled project.
● The applicant must acknowledge and approve the service-related terms and conditions
FAQ
What are the specifications of the land bound by fencing?
The vacant lands must be fenced according to the main axes targeted in the first phase in the five cities: (Riyadh, Makkah, Madinah, Dammam, Jeddah), which are specified on the geographical explorer on the Baladi platform https://balady.gov.sa//Services?id =237
FAQ
What are the stages of applying for the service of issuing a building permit?
In the event that there is a cadastral decision sourced from my country, the application is made on Baladi Services > Construction Permits Services > Issuing a Building Permit Service > Selecting the cadastral decision to apply for > Fill in the required data and send a request to a classified engineering office.
FAQ
What are the stages of monitoring an emergency excavation?
● Initiation of emergency works
● Completion of emergency works
● Completion of emergency works
FAQ
?What are the standards for CBC